2nd Quarter of 2015 Finished and On-going Projects (2)

NAME OF PROJECT LOCATION AMOUNT SOURCE OF FUNDS DATE STARTED DATE COMPLETED   REMARKS
Repainting of Tree trunks along Anao National Road Brgy SFW to Doña Carmen 48,100 MUNICIPAL EDF 3/6/2015 complete
 Renovation of Barangay Multi-Purpose Hall Roofing System POBLACION 229,999.86 MUNICIPAL/ BRGY EDF 12/15/2014 3/4/2015 complete
Reblocking Provincial Road along Brgy. Hernando- San Juan Hernando- San Juan 303,698.35 MUNICIPAL EDF 12/15/2014 1/30/2015 complete
 Concreting of Palarca Road  Rizal  761,261.44  MUNICIPAL EDF  12/15/2014 1/30/2015 complete
Intallation of Ø100mm Water Distribution line Casili 1,399,957.5 MUNICIPAL EDF 2/19/2015 on-going
Improvement of Rizal Cross-drains Rizal 1,199,958.24 MDRRMF for NTP
REHAB/ EXPANSION/ UPGRADING of LEVEL III WATER SYSTEM (Construction of 100cu.m. Capacity Elevated Water Tank) Casili 3,500,000 BUB Project Bidded last June 23